1) To undertake a full feasibility study, prepare preliminary
engineering design and tender documents and,
2) To conduct an independent Environmental and Social
Impact Assessment (ESIA) and prepare a Resettlement
Action Plan (RAP) for the 330 kV WAPP Ghana –
Burkina – Mali Interconnection Project

Countries
Sector
Region
Total Cost
4499506
COMMITTED (US$)
583300
Sources of Downstream Financing
13% funded by NEPAD-IPPF
AFD USD 2,183 million
WB USD 1,702 million
WAPP Contribution USD 0,030 million
Status